Fort Collins Microgrid

Current status, energy mix, organizations, suppliers, equipment, controls, reported specifications, and project updates—with source-level citations.

CoverageDetailed public record
Named organizations14
System facts24
Sources reviewed7
Evidence reviewed2026-07-20

The Fort Collins entry is the municipal FortZED Renewable and Distributed Systems Integration demonstration, not a military installation and not one co-located generator plant. From 2008 through 2013, Fort Collins Utilities aggregated PV, methane and natural-gas CHP, conventional generators, microturbines, fuel cells, thermal storage, controllable loads, and vehicle-to-grid assets at roughly five participant locations on two distribution feeders. A second phase intentionally islanded a smaller microgrid linking Colorado State University's Engines and Energy Conversion Laboratory with the Northside Aztlan Community Center.

Research status
Demonstration completed and no longer operating as an integrated project. City material says Phase I achieved a 20–30% peak-demand reduction on the two feeders and Phase II demonstrated the EECL–Northside Aztlan microgrid with cybersecurity safeguards. A 2020 NREL retrospective says the project was operational in 2012 but was disbanded in 2017 because of regulatory factors, historic distribution practices, and the natural end of the roughly ten-year collaboration. Individual participant assets may have continued independently, but the central FortZED dispatch system should not be represented as current.
Historical classification
CHP
Reported capacity
See component specifications
Coordinates
40.59284, -105.06860
Evidence note: “Every company” cannot be proven from public material alone. This page lists every organization found in the recovered record and reviewed sources, preserves unknown roles, and explicitly marks undisclosed controller or equipment details.

Project delivery

Who was involved in Fort Collins Microgrid?

14 publicly identified organizations. Where a recovered source named a participant without explaining its work, the role remains explicitly unspecified.

Organization

Advanced Energy

Publicly named participant; role not specified in the recovered record [1]

Organization

Advanced Energy, Woodward, Eaton, Brendle Group, and Caterpillar

Technology partners respectively associated with PV inverters, mixed-fuel and generator controls, switchgear/power components, demand-management analysis, and distributed generation. [4][3]

Organization

Brendle

Publicly named participant; role not specified in the recovered record [1]

Organization

City of Fort Collins / Fort Collins Utilities

Project lead, prime contractor, electric utility, feeder operator, and host of municipal generation, load-control, thermal-storage, and vehicle-to-grid assets. [2][3][5]

Organization

Colorado State University

Publicly named participant; role not specified in the recovered record [1]

Organization

Colorado State University / InteGrid Laboratory

Demonstration-site operator and R&D partner for controls, PHEV/V2G, simulation, mixed distributed generation, and the Phase II intentional-islanding microgrid. [4][5]

Organization

Eaton

Publicly named participant; role not specified in the recovered record [1]

Organization

InteGrid

Publicly named participant; role not specified in the recovered record [1]

Organization

Johnson Controls

Publicly named participant; role not specified in the recovered record [1]

Organization

Larimer County

Participant and host of parking-garage PV and controllable loads. [4][3]

Organization

New Belgium

Publicly named participant; role not specified in the recovered record [1]

Organization

New Belgium Brewing

Major commercial demonstration site for PV, process-methane CHP, thermal storage, smart metering, and demand response. [4][3]

Organization

Spirae

Technology partner for the smart-grid platform, distributed-resource/power-management system, asset interfaces, and integration at the InteGrid laboratory. [4][3][6]

Organization

U.S. Department of Energy / National Energy Technology Laboratory

Federal RDSI program sponsor and project-management organization; DOE provided about $6.696 million of the $11.798 million project value. [3][7]

System evidence

Energy mix, capacity, and specifications

Values can describe different project phases, generation sources, storage systems, or other components. Source citations are attached to each figure so discrepancies remain visible.

KW Solar
345 [1]
KW Gas/Diesel
760 [1]
KW Fuel Cell
5 [1]
Resources under management
NREL's 2020 retrospective reports 4 MW of generation plus 760 kW of demand-side/load-shed resources; DOE's project page describes more than 3.5 MW of aggregated DER across approximately five locations [6][2]
2008 design inventory
3,988.7 kW across generation, thermal storage, vehicle-to-grid, and load-shedding line items; this early design total is not a current plant nameplate and not every item is independently confirmed as commissioned [4]
Peak-load objective and outcome
Minimum objective 15%, target 20–30%; city and NREL closeout material report 20–30% peak-demand reduction on the two feeders [2][5][6]
Project duration
October 1, 2008 through September 30, 2013 for the DOE project; FortZED collaboration later disbanded in 2017 [3][6]
Project value
$11,797,949 total: $6,695,880 DOE share and $5,102,069 non-DOE share [3]
2008 New Belgium design resources
200 kW new PV; 292 kW Gauscor methane CHP; 650 kW Cat 3508C methane CHP; 135 kW thermal storage; 160 kW load shedding [4]
2008 InteGrid laboratory design resources
Two 80 kW Onan natural-gas gensets, one 300 kW Cat natural-gas genset, 80 kW Ingersoll Rand and 80 kW Bowman microturbines, 100 kW wind-turbine simulator, and two Plug Power fuel cells totaling 10 kW [4]

Controls and hardware

Equipment and controller details

Manufacturer and model are shown only when a source names them. Generic descriptions are not converted into guessed product assignments.

01

Distributed energy-management platform

Spirae

Central platform modeled and monitored feeder and asset state, issued dispatch commands, tracked response, and interfaced to local controllers and building systems. NREL credits standardized central control with automatically dispatching multiple owners' DER for demand reduction. [4][6]

02

New Belgium PV inverter

Advanced Energy

Specified for the 200 kW new PV array in the 2008 design inventory; model and final as-built count are not stated. [4]

03

New Belgium process-gas CHP

Gauscor / Caterpillar — Gauscor CHP and Cat 3508C CHP

The design listed a 292 kW Gauscor unit with Woodward fuel-blending controls and Eaton switchgear plus a 650 kW Cat 3508C, both using brewery process methane. [4]

04

InteGrid laboratory generation

Cummins/Onan, Caterpillar, Ingersoll Rand, Bowman, and Plug Power

The 2008 test-bed design included natural-gas gensets, two makes of microturbine, a Cummins diesel-driven induction-generator wind simulator, and two fuel cells. These laboratory devices supported integration testing and should not be described as renewable generation deployed across the city. [4]

05

Vehicle-to-grid demonstrators

Ford — Escape plug-in hybrid

Two city-fleet PHEVs were listed at 10 kW combined in the early design. Public closeout sources reviewed do not give battery size or verified delivered V2G energy. [4]

06

Switchgear and generator controls

Eaton / Woodward

Eaton supplied or developed switchgear/power components and Woodward contributed power management and mixed-fuel controls across project sites; individual final device models are not consistently disclosed. [4][3]

Technical record

Architecture, performance, and project updates

Concise technical facts, milestones, operating results, and later developments. Dated notes distinguish historical design claims from current evidence.

  • Storage

    thermal storage [1]

  • Generation

    solar PV, [1]

  • Generation

    Solar CHP, [1]

  • Virtual multi-site architecture

    Phase I coordinated assets at municipal facilities, New Belgium, CSU, Larimer County, and the InteGrid laboratory over two utility feeders. The aggregate resource figure therefore combines generation, storage-like thermal loads, and demand response owned by several parties rather than describing one fenced microgrid plant. [2][4][6]

  • Phase II islanding

    The later phase demonstrated an intentionally islanded microgrid comprising CSU's Engines and Energy Conversion Laboratory and the Northside Aztlan Center, including advanced cybersecurity safeguards for control communications. [5][3]

  • Resource diversity

    DOE lists PV, microturbines, dual-fuel CHP using process methane, reciprocating engines, backup generators, a wind simulator, V2G plug-in hybrids, fuel cells, HVAC/process load shedding, thermal storage, and efficiency upgrades. The mix was designed to test dispatch and verification, not maximize renewable-energy percentage. [2]

  • Outcome

    The project met its peak-reduction demonstration objective and advanced multi-building control, but did not achieve the original vision of a net-zero-energy district before the collaboration ended. NREL identifies stakeholder cooperation, regulatory structure, and existing utility practices as important lessons. [5][6]

  • Evidence boundary

    The detailed equipment list is a 2008 design snapshot, while later DOE, city, and NREL sources validate aggregate scale and outcomes. No current integrated FortZED controller operation or comprehensive inventory of surviving participant equipment was located; legacy solar, fuel-cell, gas/diesel, and thermal figures should not be presented as a current energy mix. [4][2][6]

Provenance

7 sources

Primary owner, government, university, supplier, and engineering sources are preferred. Archived references preserve claims whose original pages moved or disappeared.

  1. [1]
    Recovered Microgrid Projects record

    Internet Archive · Archived source · captured 2021-04-20

  2. [2]
  3. [3]
    City of Fort Collins RDSI Project Fact Sheet

    U.S. Department of Energy / National Energy Technology Laboratory · Primary source

  4. [4]
    DER Integration for Peak Load Management — DOE RDSI City of Fort Collins

    Spirae / U.S. Department of Energy · Primary source

  5. [5]
  6. [6]
    Connected Communities: A Multibuilding Energy Management Approach