Nova is IGO's remote nickel-copper-cobalt operation in Western Australia's Fraser Range. Its power system evolved from a 19 MW diesel station to a battery-free solar-diesel hybrid in 2019 and then to an engine-off hybrid with approximately 16 MW total solar, a 12 MW/12 MWh BESS and two synchronous condensers. The archived 6.7 MW solar/20 MW diesel figures reflect the original contract/design scale, while Zenith's current as-built account reports 5.5 MW initial solar and 19 MW diesel before the 10.2 MW relocatable-solar expansion.
- Research status
- Operational, with the renewable expansion commissioned and engine-off operation demonstrated. IGO's FY2023 report says the new solar farm and battery were commissioned and achieved Nova's first period on 100% renewable power; later company material lists the full 16 MW-solar/12 MW-battery system as installed. The power system also experienced a major diesel-engine-room fire in December 2022 that shut the mine for 18 days before 14.9 MW of temporary generation restored operations. IGO now expects the Nova mine to reach end of life in late 2026, making the expansion's relocatable design important; no public post-closure destination or current battery-health data was found.
- Historical classification
- Industrial
- Reported capacity
- See component specifications
- Coordinates
- -31.82323, 123.19103