Oceania & Pacific / Commercial & demonstration

Pearl Harbour

Organizations, planners, suppliers, equipment, controls, and reported system specifications—with source-level citations.

CoverageDetailed public record
Named organizations6
System facts9
Sources reviewed3
Last researched2026-07-19

The Joint Base Pearl Harbor-Hickam SPIDERS Phase I microgrid was a federal cyber-secure controls demonstration integrating diesel generation, solar, uninterruptible loads, black-start capability, and grid-tied export. Federal sources report 150 kW solar and 2.4 MW diesel; the older directory's wind and storage figures are retained separately as unverified historical claims.

Research status
SPIDERS Phase I demonstration completed and operated in the cited period
Historical classification
Military
Reported capacity
1,250 kW
Coordinates
21.34451, -157.97489
Evidence note: “Every company” cannot be proven from public material alone. This page lists every organization found in the recovered record and reviewed sources, preserves unknown roles, and explicitly marks undisclosed controller or equipment details.

Project delivery

Who was involved in Pearl Harbour?

6 publicly identified organizations. Where a recovered source named a participant without explaining its work, the role remains explicitly unspecified.

Organization

Hawaiian Electric Company

Local utility and grid-interconnection participant [3]

Organization

Joint Base Pearl Harbor-Hickam

Host installation and microgrid operator [2]

Organization

U.S. Army Engineer Research and Development Center — Construction Engineering Research Laboratory

SPIDERS engineering and technical lead [2]

Organization

U.S. Department of Defense

Installation owner and SPIDERS program sponsor [2][3]

Organization

U.S. Department of Energy

SPIDERS program and technical partner [2][3]

Organization

U.S. Department of Homeland Security

SPIDERS cyber-security program partner [3]

System evidence

Reported capacity and specifications

Values can describe different project phases or components. Source citations are attached to each figure so discrepancies remain visible.

KW Solar
146 [1]
KW Wind
50 [1]
SPIDERS solar PV
150 kW [2]
SPIDERS diesel generation
2.4 MW [2]
Demonstrated renewable penetration
Solar penetration reached 90% in testing [2]
Grid-tied export
Approximately 1 MW demonstrated [2]
Archived alternate configuration
146 kW solar, 50 kW wind, and 1,250 kW storage; equipment identities not stated [1]

Controls and hardware

Equipment and controller details

Manufacturer and model are shown only when a source names them. Generic descriptions are not converted into guessed product assignments.

01

Microgrid controls

Model not publicly disclosed

Remote HMI, black-start sequencing, solar integration, and secure generation control were demonstrated; the reviewed federal overview does not name the controller model. [2]

02

Uninterruptible power supply

Model not publicly disclosed

UPS supported designated uninterruptible loads; manufacturer and energy capacity not stated. [2]

Provenance

3 sources

Primary owner, government, university, supplier, and engineering sources are preferred. Archived references preserve claims whose original pages moved or disappeared.

  1. [1]
    Recovered Microgrid Projects record

    Internet Archive · Archived source · captured 2021-04-20

  2. [2]
    JCTD SPIDERS Technical Overview — Phases 1–3

    U.S. Department of Energy / ERDC-CERL · Primary source

  3. [3]
    Energy Surety Microgrids — SPIDERS technical approach

    U.S. Department of Energy / Sandia National Laboratories · Primary source