The widely announced Ulleung-do energy-independent island project was never completed. The 2014-2016 concept went through a major redesign—from a fuel-cell-heavy portfolio to one dominated by geothermal—but economics deteriorated after the government changed its power-purchase support and public acceptance of geothermal collapsed after the 2017 Pohang earthquake. Gyeongsangbuk-do formally abandoned the KRW 268.5 billion program in 2018 after approximately KRW 11.6 billion had been spent, and the special-purpose company was subsequently liquidated. Planned generation and storage capacities are therefore design targets, not installed assets.
- Research status
- Cancelled/abandoned in 2018; project company liquidated. No evidence that the proposed renewable microgrid was commissioned.
- Historical classification
- Island
- Reported capacity
- 11 MW
- Coordinates
- 37.48442, 130.90580