Goldwind Demonstration Microgrid

CHP · Operational
3,730KW

Organizations Involved

Additional Details

Energy control system of the smart micro grid

  • Integrate and maximise the proportion of renewable energy power generation
  • Coordinate island and the grid-connected operation whilst ensuring the stability of power supply
  • Adaptable control interface able to control different generation, load and storage technologies
  • Flexible configuration allowing customised system operation and control strategy

 

The power storage unit is composed of a 200KW Vanadium redox flow cell, a 200 lithuim cell and a 200KW super capacitor. The first two storage units can last four hours each and the last for 40 seconds.

Location

G 2 Jing Hu Gao Su, Tongzhou Qu, Beijing Shi, China