Evidence from 197 project records
Microgrid controllers and software in real projects
Who supplied the control systems that run real microgrids, and which planning and test software shows up in their records.
THE SHORT ANSWER
132 of 197 projects document a controller, energy-management or SCADA system, and 102 name the supplier. 77 different suppliers appear. ABB (including Powercorp) leads with 14 projects; no other supplier appears in more than 5.
The controller usually came with the equipment
The clearest pattern in the records is that the control system was often bought with the hardware. Remote and island projects name inverter, battery or generator makers as the controls supplier: ABB and Powercorp on remote towns, islands, Antarctic stations and a copper mine, mostly with ABB’s Microgrid Plus system; Leonics and SMA on solar-diesel and solar-battery mini-grids; Princeton Power Systems on Alcatraz. Campus, community and military projects more often name a dedicated controls company: Schneider Electric, SEL, Siemens, IPERC or PXiSE.
The long tail matters as much as the leaders. Only 16 of the 77 suppliers appear in more than one project. For an owner, that means the controller decision is also a decision about who will support the site for the next 20 years. Alcatraz shows why: its record notes an October 2019 energy-management failure that left the diesel generators carrying the island until repairs.
Controller suppliers
Controller and EMS suppliers in the directory
The 16 most frequent suppliers of microgrid controllers, energy-management and SCADA systems across the researched records, with the projects that name them.
Planning and test software
Software named in the project records
Planning and engineering tools rarely appear in as-built records, so each mention below is worth reading. Modeled results are not metered performance.
| Software | How it was used | Projects |
|---|---|---|
| HOMER | Leonics’ case study on these mini-grids is published on HOMER Energy’s website; HOMER Pro modeled the five Hempstead–Port Washington nodes; Baron Techno Park’s reported energy mix is a HOMER model output, not metered data. | Banggi Island Microgrid, Bario, Kema Microgrid, Hempstead – Port Washington Microgrid Feasibility Study, Baron Techno Park |
| DER-CAM | Berkeley Lab’s optimizer sized and dispatched the NY Prize feasibility studies, and its Operations DER-CAM scheduled the Fort Hunter Liggett battery day ahead with 15-minute re-optimization. | Brookhaven Microgrid Feasibility Study, Long Beach Microgrid Feasibility Study, Port Jefferson Microgrid Feasibility Study, Southampton Microgrid Feasibility Study, Fort Hunter Liggett |
| REopt | NLR analyzed Alcatraz dispatch with REopt before a revised load-following strategy, and published a REopt case study on the Fort Carson battery. | Alcatraz Island Microgrid, Fort Carson Microgrid |
| ETAP and OPAL-RT | UC Irvine’s ETAP network model supported steady-state, dynamic and control studies, and a controller was tested against that model on an OPAL-RT real-time simulator. | UC Irvine Microgrid |
| Hardware-in-the-loop testing | Borrego Springs’ DOE/NREL project paired controller hardware-in-the-loop work with field tests of a battery-led black start; Otis tested high-wind operation only in hardware-in-the-loop; UCSD and TECNALIA run power-hardware-in-the-loop testbeds. | Borrego Microgrid, Otis Air National Guard Base, UCSD Microgrid, Tecnalia Microgrid |
What these projects teach a new buyer
- Separate the planning model from the controller. HOMER, DER-CAM and REopt sized and priced these systems; the controllers that run them came from different companies. A planning result is a design basis, not an operating guarantee.
- Do not read model output as performance. The Baron Techno Park record warns that its published energy mix is a HOMER model result, not metered production.
- Test the controller before you need it. Otis Air National Guard Base never ran its planned 120-hour islanding test; high-wind operation was tested only in hardware-in-the-loop simulation.
- Plan for ownership changes. Suppliers in these records have been acquired, renamed or left the market. Ask any controller vendor for a written support and upgrade path.
Choosing software for a new microgrid
These records show what was used. For what to use now, MicrogridModeler’s microgrid software comparison covers more than 70 current tools across planning, engineering, controllers, energy management and fleet operations, with 2026 list prices, five-year license costs and the IEEE 2030.7 and 2030.8 questions to put to a controller vendor.
Quick answers
Questions about microgrid controllers and software
Which company supplies the most microgrid controllers?
In this directory’s 197 project records, ABB (including Powercorp) appears most often, in 14 projects, largely remote towns, islands and Antarctic stations. The records are historical and selective, so the count describes this sample, not today’s market share.
Is the microgrid controller usually a separate product?
Often it is not. In many remote and island projects the inverter, battery or generator supplier also supplied the controller, so the control choice was made when the equipment was chosen. Campus and military projects more often name a dedicated controls supplier such as Schneider Electric, SEL, Siemens or IPERC.
What software is used to plan a microgrid?
The project records name HOMER, DER-CAM and REopt for planning and sizing, ETAP for network studies, and OPAL-RT and other hardware-in-the-loop platforms for controller testing. MicrogridModeler’s guide compares more than 70 current planning, engineering, controller and fleet software tools.
Why do microgrid controller suppliers matter after construction?
The controller decides when the site islands, which loads are shed and how generators and batteries are dispatched for decades. Several suppliers in these records have since been acquired, renamed or left the market, so support, spare parts and software updates should be planned before purchase.